WHAT'S GOING ON HERE? Temporary lane closures at Markham’s 16th Ave., Williamson Road

Improvements being made; project 65 per cent complete

Yorkregion.com
Dec. 9, 2019
Simone Joseph

Improvements are being made to the intersection of Markham’s 16th Avenue and Williamson Road that will require temporary lane closures. The improvements involve installation of a new traffic signal.

JUST THE FACTS

Are we there yet? Are we finished? Improvements are being made now to 16th Avenue and Williamson Road. The project is 65 per cent complete.

When will it end?

Improvements are scheduled to finish by the end of 2019.

Cost?

This intersection improvement costs approximately $150,000.

Traffic impact

The intersection will remain open to traffic during construction and access will be maintained. However, temporary lane closures will be required between 9:30 a.m. and 3:30 p.m. for construction.