Corp Comm Connects


Two Cranes Raised as Forming Begins for The Met in Vaughan

Urbantoronto.ca
Sept. 13, 2017
By Jack Landau

 

















It is just under three months since we last visited the Vaughan construction site of Plaza and Berkeley's The Met, a 35-storey, Quadrangle-designed condominium and townhome development on Jane Street just north of Highway 7, and walking distance from Vaughan Metropolitan Centre subway station which opens on December 17th. At the time of our last update in June, shoring and excavation were wrapping up, with dewatering equipment in use to manage the site's high water table.

In the months since, a first tower crane has been installed at the east end of the site, allowing for the start of forming for the first of the building's three underground parking levels. Views of the site's east end show that a large section of the P3 level has been built, with columns and floors for the P2 level above now being poured above.

The project reached another milestone this week when a second tower crane was erected at the west end of the site, to continue the work closer to Jane Street. This is also where the development's podium and tower will rise. The east crane's job will be complete once townhome blocks are finished at its end.

The installation of the west crane was carried out on Tuesday morning, continuing into the afternoon. Crane sections were delivered to the site by flatbed trucks, which were then driven down a dirt ramp to the base of the pit. From here, a mobile hydraulic crane unloaded crane components and hoisted them up to awaiting crews who bolted the components together.

Following the crane's mast section being bolted into place, the crane cab was hoisted aloft.

Once the crane cab arrived at the top of the mast section, it was carefully moved into place before being secured by construction crews.